Important Facts and Formulae |
|
(1)P can complete a work in 12 days working 8 hours a day.Q can complete the same work in 8 days working 10 hours a day.If both P and Q work together,working 8 hours a day,in How many days can they complete the work?(Asked in Bank PO Exam 1999)
- 60/11
- 61/11
- 71/11
- 72/11
(2)A and B can do a work in 12 days,B and C can do the same work in 12 days.A,B and C together can finish it in 6 days.A and C together will do it in:
- 5 days
- 47/6 days
- 10 days
- 47/3 days
(3)A and B can do a work in 8 days,B and C can do the same work in 12 days.A,B and C together can finish it in 6 days.A and C together will do it in:
- 4 days
- 6 days
- 8 days
- 12 days
(4)A and B can do a piece of work in 72 days,B and C can do it in 120 days,A and C can do it in 90 days.In what time can A alone do it?
- 80 days
- 100 days
- 120 days
- 150 days
(5)A works twice as fast as B.If B can complete a work in 12 days independently,the number of days in which A and B can together finish the work is:
- 4 days
- 6 days
- 8 days
- 18 days
(6)A is thrice as good a workman as B and therefore is able to finish a job in 60 days less than B.Working together,they can do it in:
- 20 days
- 45/2 days
- 25 days
- 30 days
(7)A and B can do a job together in 7 days.A is 7/4 times as efficient as B.The same job can be done by A alone in:
- 28/3
- 11 days
- 49/4
- 49/3
(8)A can do a work in 15 days and B in 20 days.If they work on it together for 4 days,then the fraction of the work that is left is:
- 1/4
- 1/10
- 7/15
- 8/15
(9)X and Y can do a piece of work in 20 days and 12 days respectively.X started the work alone and then after 4 days Y joined him till the completion of the work.How long did the work last?(bank Po 2004)
- 6 days
- 10 days
- 15 days
- 20 days
(10)A and B can do a piece of work in 30 days,while B and C can do the same work in 24 days and C and A in 20 days.They all work together for 10 days when B and C leave.How many days more will A take to finish the work?
- 18 days
- 24 days
- 30 days
- 36 days
Answers
Question Number | Answer |
1 | 60/11 |
2 | 10 days |
3 | 8 days |
4 | 120 days |
5 | 4 days |
6 | 45/2 days |
7 | 11 days |
8 | 8/15 |
9 | 10 days |
10 | 18 days |